Thomas More Square, London
Instruction Synopsis Propitas were instructed to provide Project Management, Employer’s Agent and Quantity Surveying services on the refurbishment and vertical and horizontal extension to Building 6 at Thomas More Square. The works comprised extension to the front façade providing a new architectural curtain wall constructed … Read More
Camden Street, Camden, London
Instruction Synopsis Propitas were appointed to act as Project Manager and Employer’s Agent in respect of a mixed use new-build scheme in Camden, North West London. The project comprised the initial demolition of an existing factory building, and the subsequent construction of a 7 storey … Read More
Crimscott Street, Bermondsey, London
Instruction Synopsis Propitas were appointed to act as Project Manager and Employer’s Agent in respect of a mixed use new-build scheme in Bermondsey, South East London. Our client purchased the site in 2018 and the project comprised the construction of an 8 storey structure within … Read More
Dilapidations Assessment Report
Instruction Synopsis We completed a dilapidations assessment study and report for a large private members club on Pall Mall, London. The property comprises c. 85,000 sq ft arranged over lower ground, ground and five upper floors. The property is Grade 1 listed, was designed by … Read More
Portfolio Schedules of Condition
Instruction Synopsis Propitas were instructed on behalf of a client in the process of acquiring another business. As part of the transaction they required a record of the condition of 6 no. properties which were subject to existing occupational leases. The properties comprises 5 no. … Read More
Unit 2 Crompton Fields, Crawley
Instruction Synopsis Propitas were appointed by London Metric Property PLC to undertake design, Project Management and Contract Administration of the refurbishment of Unit 2 Crompton Fields, a commercial property in Crawley. The property comprised a steel portal framed terraced warehouse unit with a block-built … Read More
Sabre House, Tottenham
Instruction Synopsis Propitas were appointed by London Metric Property PLC to undertake pre-acquisition, design, project management and contract administration for the refurbishment of Sabre House, a commercial property in Tottenham, London. The property comprised two adjoining steel framed warehouses with extensive mezzanine structures throughout, and … Read More
2 Sheen Road, Richmond
Instruction Synopsis Propitas were appointed by Boultebee Brooks Real Estate as Project Manager and Cost Consultant on the refurbishment of 2 Sheen Road, an office building in Richmond, London. The property comprised a concrete framed structure and floors, with raised access flooring and brick-built … Read More
4/5 Lochside, Edinburgh Park, Edinburgh
Instruction Synopsis Propitas were instructed to project manage the implementation of a high specification serviced office scheme to circa 42,000 sq ft of accommodation over three floors. We negotiated the Design & Build Contract with a preferred contractor, spending time to hone the design and … Read More
3 SIDNEY STREET, CAMBRIDGE
Instruction Synopsis Propitas was appointed to carry out a pre-acquisition building survey of this Grade II Listed property located in the heart of Cambridge, on behalf of an investor. This highly ornate, Jacobean building occupies a prominent dual frontage position, and has been occupied by … Read More
Waterstones 2019, Nationwide
Instruction Synopsis Propitas was appointed to inspect and provide condition reports on Waterstones’ entire property portfolio across the UK, Republic of Ireland and mainland Europe. These properties ranged from modern high street stores, to prominent Grade I listed buildings. Following our appointment, we conducted a … Read More
Minworth Central, Minworth, Birmingham
Instruction Synopsis Propitas were instructed to undertake a pre-acquisition survey and prepare a detailed schedule of condition of this circa 164,000 sq ft distribution centre on behalf of an international logistics operator. A number of significant elements of disrepair were identified as part of our … Read More
Units 1 To 6, Aylesham Industrial Estate, Bradford
Instruction Synopsis Propitas were instructed on behalf of Wesleyan Assurance Society to manage the refurbishment of six industrial units at Aylesham Industrial Estate, Bradford. The client took back vacant possession from the former tenants at various stages, and elected to refurbish the units in order … Read More
Investment Office Building, Amersham
Instruction Synopsis We were appointed by the freeholder of this office to inspect this large office towards the end of the tenant’s 15 year FRI lease. The headquarter office building was constructed in circa 2002 and provides approximately 23,000 square feet over ground and first … Read More
Station Approach, West Byfleet
Instruction Synopsis Our client Altitude Real Estate Investors acquired the site in mid 2015 which comprised a 1960’s office building over an existing town centre retail commercial centre. Initially Propitas advised the client during due diligence of the acquisition. Working with the Local Planning Authority, … Read More
The Belvedere, Tunbridge Wells
Instruction Synopsis Propitas are appointed by Altitude Real Estate Investors as Project Managers in connection with the mixed-use redevelopment of a strategic site in central Tunbridge Wells close to the main line train station. The proposed development comprises 108 residential apartments above 65,000 sq ft … Read More
Leander House, Solent Business Park, Fareham
Instruction Synopsis Propitas were instructed by Wesleyan Assurance Society to carry out a pre-acquisition survey of this 25-year-old office building, which comprises circa 45,000 sq ft of office accommodation on a ‘Listed X’ status site. We were appointed to lead the technical team, which included … Read More
Evolution 50, Andover
Instruction Synopsis Propitas were instructed by Laleham Healthcare to undertake a pre-acquisition survey prior to the intended long leasehold occupation by our client. The property comprises a modern warehouse unit constructed in 2015 offering circa 52,000 sq ft of internal accommodation in addition to a … Read More
Ashley Park House, Walton-on-Thames
Instruction Synopsis We were appointed by KBC to inspect their head office and prepare a dilapidations assessment report for budgetary and strategy purposes during the last few years of their 15 year FRI lease. The headquarter office building was constructed in circa 2001 and provides … Read More
Langley Studios, Langley, Slough
Instruction Synopsis We were appointed by Netflix to establish the state of repair of the property and prepare an estimate for the potential dilapidations liability for budgetary purposes prior to Netflix taking a new lease on the studios and thereby inheriting any dilapidations liability of … Read More